Thames Valley: Crossrail launch delayed again
Crossrail has been delayed until 2021 - with the Elizabeth Line launch unlikely to be before March that year.
Mark Wild, chief executive of Crossrail, said: “The Crossrail project has made good progress over recent months as the new plan to complete the Elizabeth line is implemented by the supply chain.
“A key focus during 2019 has been finalising the stations, tunnels, portals and shafts. By the end of the year, Custom House, Farringdon and Tottenham Court Road stations will be complete and the project is on track to finish fit-out of the tunnels in January. The central section will be substantially complete by the end of the first quarter in 2020, except for Bond Street and Whitechapel stations where work will continue.
“The two critical paths for the project remain software development for the signalling and train systems, and the complex assurance and handover process for the railway; both involve safety certification for the Elizabeth line. These must be done to the highest quality standards to ensure reliability of the railway from day one of passenger service.
“Crossrail Ltd will need further time to complete software development for the signalling and train systems and the safety approvals process for the railway. The Trial Running phase will begin at the earliest opportunity in 2020, this will be followed by testing of the operational railway to ensure it is safe and reliable.
“Our latest assessment is that the opening of the central section will not occur in 2020, which was the first part of our previously declared opening window. The Elizabeth line will open as soon as practically possible in 2021. We will provide Londoners with further certainty about when the Elizabeth line will open early in 2020.
"Our detailed cost forecasts continue to show that the project’s costs will increase due to programme risks and uncertainties. The latest projections indicate a range of between £400 million to £650 million more than the revised funding agreed by the Mayor, Government and Transport for London in December 2018.
“We are doing everything we can to complete the Elizabeth line as quickly as we can but there are no short-cuts to delivering this hugely complex railway. The Elizabeth line must be completed to the highest safety and quality standards.”
Reacting to the news that Crossrail has announced another delay to the completion of the Elizabeth Line to 2021, Federation of Small Businesses (FSB) Mike Cherry, said:
“Another delay to Crossrail is disappointing to see and will leave a sour taste in the mouths of businesses and commuters who had been preparing for the start of the service in 2020.
“This delay is fast-becoming a national embarrassment.
“Small businesses along the route of the Elizabeth Line, from Berkshire to Essex and across London, have long been preparing for the start of the service in early 2020.
“This delay means another year of extra construction costs, another year of lost revenues and another year of strains on an already bursting public transport system.”